Build-Out of New Retail Shops on Track
August 24, 2011
With Interior wall framing complete and “in-wall” rough-in of MEP (Mechanical/Electrical/Plumbing) trades close behind, sheet rock installation is scheduled to begin this week.
Plumbing piping has been installed and tested. Primary Electrical Service installation is well underway.
Framing of demising walls for retail Shop–A is complete. These walls serve to divide the area into five separate tenant spaces.
Overhead MEP rough-in moves forward.
In-wall plumbing and framing of restrooms is nearing completion. Sheetrock work is scheduled to begin this week.