Patterns of the Future
The pattern of future concrete pours took shape this week with forms being placed for the diamond detailing that is planned for the pedestrian walkway.
The Pedestrian Plaza will consist of two types of concrete detailing to create the pattern noted in the above design. The darker areas will be exposed aggregate, while the lighter areas will consist of integral colored concrete.
Work moved forward this week with the fine grading of future road ways surrounding the Grundy Town Center. Placement of stone sub-base and curb & gutter operations is scheduled to begin early next week.
Installation of electrical equipment that will service the elevators, escalators and cartveyor are taking place on the ground floor of the Atrium.
Final terminations of electrical feeds and controls for the escalators and cartveyor are on-going and should be completed by next week.
Installation of the remaining flooring was completed as scheduled. The flooring consists of VCT and vinyl wood flooring in the Sales Area, ceramic tile in the Atrium and Bathrooms and non-slip surfaces in the Bakery\Deli area.























I left Grundy in Sept. 1964, I am looking forward to visit my old hometown and checkingit out in near future.