Welcome to Raising Grundy, a blog chronicling the re-construction of a special town in the Highlands section of Virginia. The new Center bridges two sides of the community—traditional township with new development—connecting the people who make this place a proud home. We look forward to seeing continued positive economic impact unfold for the whole region. It was a pleasure to work with the good people of Grundy. - The Stewart Perry Company
Official Ribbon Cutting Ceremony Of Grundy Town Center
There was no shortage of people anxious to try their hand at cutting the ribbon for the official grand opening of Wal-Mart. The anchor store is the first of a variety of both retail shops and restaurants that will bring to fruition, the raising of Grundy.
Senator Puckett offers his congratulatory speech and dedication to the town of Grundy at the realization of their New Town Center.
A big cheer for the new opportunities made available to the town’s residents. Grundy H.S. cheerleaders rang out the Wal-Mart cheer!
The store team’s introduction to their patrons…
After raising the American flag and Virginia’s State flag, the young men of Troop 740 show their respect for the symbols of their country and state.
Moving Ahead with Retail Shops
Overhead rough-in and MEP trim-out work is complete. Flooring installation is ongoing.
Upfit activities on this space are on hold, awaiting final pricing and approval.
Overhead rough-in and MEP Trim-out work is complete. With final inspection, ceiling tile installation will begin early next week.
Overhead rough-in and MEP trim-out work is complete. With final inspection, ceiling tile installation will begin early next week.
Overhead rough-in and MEP trim-out work is complete. With final inspection, ceiling tile installation will begin early next week.
Slat wall, ceiling tile and lighting installation is complete. Flooring installation is ongoing. Anticipated opening date is the week of September 16th.
We are pleased to announce that the Grand Opening of Wal-Mart will be Wednesday, September 14th.
Wal-Mart Receives Certificate of Occupancy!
Buchanan County Building Inspector, Wal-Mart Store Manager, IDA Officials and Stewart Perry Project Superintendent were all present for the formal transfer of the new Grundy Town Center’s CO.
Building relationships is one of the bonuses in building a project. Here you will see the Buchanan County Official – Bill Campbell, Wal-Mart Store Manager – JoJo Clemins and Stewart Perry Project Superintendent – Butch Morris celebrating a job well done!
Slat wall installation is now complete and installation of suspended ceiling system in on-going.
This location awaits final blueprints before construction can begin.
Sheet rock installation is complete and finishing is on-going. Suspended ceiling grid will be installed over the holiday weekend.
Sheet rock installation is complete and finishing is on-going. Suspended ceiling grid will be installed over the holiday weekend.
Sheet rock installation is complete and finishing is on-going. Suspended ceiling grid will be installed over the holiday weekend.
Slat wall installation is now complete and installation of suspended ceiling system in on-going.
Grundy Town Center Retail Shops Gaining Ground
Photo appreciation to Russell Belcher of Arc Lamp Productions.
Interior build-out of Shops – B moved forward, with installation of sheet rock walls. Ceiling grid and slat-wall installation, as well as MEP trim-out are scheduled to begin this week.
Interior build-out of Shops – A advanced with the installation of sheet rock.
Interior wall and overhead MEP rough-ins were completed and released for sheet rock installation.
Interior wall and overhead MEP rough-ins were completed and released for sheet rock installation.
Work in this location awaits release of final blueprints.
Interior build-out of this shop moved forward with installation of sheet rock walls. Ceiling grid and slat-wall installation, as well as MEP trim-out are scheduled to begin this week.
Build-Out of New Retail Shops on Track
With Interior wall framing complete and “in-wall” rough-in of MEP (Mechanical/Electrical/Plumbing) trades close behind, sheet rock installation is scheduled to begin this week.
Plumbing piping has been installed and tested. Primary Electrical Service installation is well underway.
Framing of demising walls for retail Shop–A is complete. These walls serve to divide the area into five separate tenant spaces.
Overhead MEP rough-in moves forward.
In-wall plumbing and framing of restrooms is nearing completion. Sheetrock work is scheduled to begin this week.